TLC has left-over large drainage pipe for sale

By Mary Alice Murphy

Joel Miller, TLC assistant superintendent, and Joseph Garcia of New Mexico Department of Transportation held what they expect to be the final meeting on the Pinos Altos, New Mexico 15, Road construction project that has been going on for about 14 months.

Miller warned that traffic will be switching back and forth, especially on 32nd Street, for at least the next couple of weeks, so they can pave one side and then the other.

He said they are trying hard to get the paving done as soon as they can. "We've had a smoothness issue. DOT has specific specs on tolerance, and they cannot be off more than ¼-inch. Southwest Concrete and Paving is our subcontractor, because we were having problems getting pavers down from Albuquerque, because they are so busy up there."

He said Southwest was working with them on the tolerance issue, which might have been caused by a mechanical issue. He said Southwest Concrete and Paving has been a good partner, and the problem could have happened with the pavers they usually use. "They are resolving it to match DOT quality specs. It'll happen."

"We have to have the paved roadway totally completed before we can set the valves and manholes in place," Miller explained. "We have lots of little things going on to finish up, so we expect to be done in mid-July or soon after. We have at least two or three more weeks of work.

"For lighting, we still have seven holes to drill to put in the poles," he said. "Six on 32nd and one down near the Silver Heights intersection. All of them are in rock, so it won't be easy. We also have a lot of signs to put up. It will take a week to a week and a half to get all the permanent signs up. We also have to finish the colored concrete in the median on P.A. Road above 32nd Street."

Other smaller projects include replacing portions of some of the concrete aprons and driveways, where "we probably let residents drive on them too soon. We will also be putting an additional gravity wall across from Peck's Body Shop. That will take a week to finish. We added a new wall at McDonald's across from R&L, but all driveways are open into McDonald's now."

DOT is checking the smoothness of the roads and sidewalks, and any that are out of tolerance will need to be fixed.

"We have to do a substantial concrete slope at the northwest corner of P.A. Road and 32nd," Miller continued. "Once the pavement is complete and the broken concrete is replaced, the sealers will come in, remove the spaces between sidewalk and gutter sections and seal them. It took about two weeks to get all the fencing up that was new or had to be replaced. The rip rap contractor was finished in a week. Just south of the Bosworth entrance, we need to put in a retaining wall to keep dirt from washing onto the roadway. We have lots of stuff happening, but it's coming together. When all is done, the seeders will come in to seed the slopes that require it. We'll get the seeding survey done, so we can give an estimate to DOT to decide if the amount we chose is what they think is needed. If we can get the seed on before the monsoons, it'll fill in quickly. It's one of the last things to do. That and the roadway striping."

He said two types of seed are used, A or B, based on the slope angle.

"I think DOT is pleased overall," Miller said. Garcia agreed.

Miller said electricians have a week or more of work to do, including drilling the seven holes for light poles.

"It's real bright out there at night," he said. "But the light doesn't spread out all over the place. It's focused on the ground."

To a question about whether there would be a light pole at the northeast corner behind the Moose Lodge to light the curve, Miller confirmed there would be. "The phone lines are high enough to clear the fixture, but the communications lines are not. They are aware of it and have to resolve it. We raised the area four feet."

In discussing the huge drainage structures that were put in along the route, Miller said that places like R&L and Peck's that used to flood in a big rainstorm, "I don't think will flood anymore."

"Several people who had problems, such as Pampered Pet and Mi Casitas on Bosworth, that were not addressed in the plans, paid TLC to do paving of driveways and ramps. We did it basically at cost, and most seem pleased with the results. After this week, we will have only five guys here doing concrete work, so if you want us to do anything, call us quickly and if we have time, we'll do it while we're still here. It will be cheaper now than if you have to pay to bring in the material and the equipment."

Miller said they are selling culvert pipe that was left over at cost, so they don't have to transport it back to Albuquerque. "We have 48-inch, 42-inch and 30-inch. Call us in the next week or so or it will be transported back north."

"We're cleaning up the materials yards we've been using," Miller said. "We have no big things left, and we are definitely ahead of schedule, as we anticipated September or October before we would be done. I would be astounded if we were here past mid-July.

"We've had a good time here," Miller said. "Yes, there were problems, but when we fixed them, people appreciated it. It's been a good job, but I'm looking forward to spending more time at home. I would get home late Friday night, have Saturday, and then be coming back on Sunday, but it's been good. We want to do the best job we can. Thanks to everyone for being reasonable."

Content on the Beat

WARNING: All articles and photos with a byline or photo credit are copyrighted to the author or photographer. You may not use any information found within the articles without asking permission AND giving attribution to the source. Photos can be requested and may incur a nominal fee for use personally or commercially.

Disclaimer: If you find errors in articles not written by the Beat team but sent to us from other content providers, please contact the writer, not the Beat. For example, obituaries are always provided by the funeral home or a family member. We can fix errors, but please give details on where the error is so we can find it. News releases from government and non-profit entities are posted generally without change, except for legal notices, which incur a small charge.

NOTE: If an article does not have a byline, it was written by someone not affiliated with the Beat and then sent to the Beat for posting.

Images: We have received complaints about large images blocking parts of other articles. If you encounter this problem, click on the title of the article you want to read and it will take you to that article's page, which shows only that article without any intruders. 

New Columnists: The Beat continues to bring you new columnists. And check out the old faithfuls who continue to provide content.

Newsletter: If you opt in to the Join GCB Three Times Weekly Updates option above this to the right, you will be subscribed to email notifications with links to recently posted articles.

Submitting to the Beat

Those new to providing news releases to the Beat are asked to please check out submission guidelines at https://www.grantcountybeat.com/about/submissions. They are for your information to make life easier on the readers, as well as for the editor.

Advertising: Don't forget to tell advertisers that you saw their ads on the Beat.

Classifieds: We have changed Classifieds to a simpler option. Check periodically to see if any new ones have popped up. Send your information to editor@grantcountybeat.com and we will post it as soon as we can. Instructions and prices are on the page.

Editor's Notes

It has come to this editor's attention that people are sending information to the Grant County Beat Facebook page. Please be aware that the editor does not regularly monitor the page. If you have items you want to send to the editor, please send them to editor@grantcountybeat.com. Thanks!

Here for YOU: Consider the Beat your DAILY newspaper for up-to-date information about Grant County. It's at your fingertips! One Click to Local News. Thanks for your support for and your readership of Grant County's online news source—www.grantcountybeat.com

Feel free to notify editor@grantcountybeat.com if you notice any technical problems on the site. Your convenience is my desire for the Beat.  The Beat totally appreciates its readers and subscribers!  

Compliance: Because you are an esteemed member of The Grant County Beat readership, be assured that we at the Beat continue to do everything we can to be in full compliance with GDPR and pertinent US law, so that the information you have chosen to give to us cannot be compromised.