Development of a proposed state-specific rule is in response to a petition from the State of Alaska

JUNEAU, ALASKA, Oct. 15, 2019 – The U.S. Department of Agriculture is seeking public comment on a draft environmental impact statement offering a range of alternatives to roadless management and a proposed Alaska Roadless Rule. If adopted, the proposed rule would exempt the Tongass National Forest from the 2001 Roadless Rule.

The USDA Forest Service will publish the documents in the Federal Register this week. The publication will begin a 60-day public comment period on the proposed rule, and on each alternative outlined in the draft environmental impact statement.

The draft environmental impact statement, prepared under the National Environmental Policy Act, provides an analysis of six alternatives, which are options, choices, or courses of action related to roadless management in Alaska. The alternatives range from no action to the removal of the Tongass from the 2001 Roadless Rule. The Department has identified Alternative 6, which is a full exemption, as the preferred alternative at this time. The full range of options are:

  • Alternative 1 takes no action and would leave all of Alaska under the 2001 Roadless Rule, including the Tongass National Forest.
  • Alternative 2 provides regulatory protection for the majority (89%) of key watersheds inside roadless areas and would convert 18,000 old-growth acres and 10,000 young-growth acres previously identified as unsuitable timber lands to suitable timber lands.
  • Alternative 3 provides regulatory protections for all key watersheds inside and outside roadless areas, creates a community priority roadless designation that allows for recreational development and timber sales under 1 million board feet, and would convert 76,000 old-growth acres and 14,000 young-growth acres previously identified as unsuitable timber lands to suitable timber lands.
  • Alternative 4 restricts harvest and road-building activities in scenic viewsheds and most (88%) key watersheds inside roadless areas and would convert 158,000 old-growth acres and 15,000 young-growth acres previously identified as unsuitable timber lands to suitable timber lands.
  • Alternative 5 would remove 2.3 million acres from roadless area designation, protects some (59%) key watersheds, and would convert 165,000 old-growth acres and 17,000 young-growth acres previously identified as unsuitable timber lands to suitable timber lands.
  • Alternative 6 (preferred) would exempt the Tongass National Forest from the 2001 Roadless Rule and is fully responsive to the State of Alaska’s petition. The alternative would remove all 9.2 million acres of inventoried roadless acres and would convert 165,000 old-growth acres and 20,000 young-growth acres previously identified as unsuitable timber lands to suitable timber lands. Conservation of roadless values would be achieved through other means, including the Tongass Land Management Plan. This is specific to the Tongass National Forest. The Chugach National Forest would remain under the 2001 Roadless Rule.

The Forest Service is scheduling a series of public meetings and subsistence hearings. A list of those meeting locations will be available on the Alaska Roadless Rule project website.

The public has until midnight Alaska time on Dec. 17, 2019, to submit comments on the documents. The documents are posted in the Federal Register and on the agency’s Alaska Roadless Rule website.

These are the ways the public can submit written comments once the notice is published:

Written comments will help inform USDA as it moves toward a final decision about an Alaska-specific roadless rule. The Secretary of Agriculture is expected to make a final decision by June 2020.

The Tongass stretches over the 500-mile-long Southeast Alaska Panhandle and covers 80 percent of the land. It is rich in natural resources and cultural heritage. Developed areas cover about 8 percent of the land. There are 32 communities, including the state capitol of Juneau, in Southeast Alaska.

News media inquiries should be made to the Forest Service Press Desk at pressoffice@fs.fed.us or call 202-205-1134.

Content on the Beat

WARNING: All articles and photos with a byline or photo credit are copyrighted to the author or photographer. You may not use any information found within the articles without asking permission AND giving attribution to the source. Photos can be requested and may incur a nominal fee for use personally or commercially.

Disclaimer: If you find errors in articles not written by the Beat team but sent to us from other content providers, please contact the writer, not the Beat. For example, obituaries are always provided by the funeral home or a family member. We can fix errors, but please give details on where the error is so we can find it. News releases from government and non-profit entities are posted generally without change, except for legal notices, which incur a small charge.

NOTE: If an article does not have a byline, it was written by someone not affiliated with the Beat and then sent to the Beat for posting.

Images: We have received complaints about large images blocking parts of other articles. If you encounter this problem, click on the title of the article you want to read and it will take you to that article's page, which shows only that article without any intruders. 

New Columnists: The Beat continues to bring you new columnists. And check out the old faithfuls who continue to provide content.

Newsletter: If you opt in to the Join GCB Three Times Weekly Updates option above this to the right, you will be subscribed to email notifications with links to recently posted articles.

Submitting to the Beat

Those new to providing news releases to the Beat are asked to please check out submission guidelines at https://www.grantcountybeat.com/about/submissions. They are for your information to make life easier on the readers, as well as for the editor.

Advertising: Don't forget to tell advertisers that you saw their ads on the Beat.

Classifieds: We have changed Classifieds to a simpler option. Check periodically to see if any new ones have popped up. Send your information to editor@grantcountybeat.com and we will post it as soon as we can. Instructions and prices are on the page.

Editor's Notes

It has come to this editor's attention that people are sending information to the Grant County Beat Facebook page. Please be aware that the editor does not regularly monitor the page. If you have items you want to send to the editor, please send them to editor@grantcountybeat.com. Thanks!

Here for YOU: Consider the Beat your DAILY newspaper for up-to-date information about Grant County. It's at your fingertips! One Click to Local News. Thanks for your support for and your readership of Grant County's online news source—www.grantcountybeat.com

Feel free to notify editor@grantcountybeat.com if you notice any technical problems on the site. Your convenience is my desire for the Beat.  The Beat totally appreciates its readers and subscribers!  

Compliance: Because you are an esteemed member of The Grant County Beat readership, be assured that we at the Beat continue to do everything we can to be in full compliance with GDPR and pertinent US law, so that the information you have chosen to give to us cannot be compromised.