In all construction zones, motorists are asked to reduce speed, obey posted signs, and use extreme caution, as well as continuing to be cautious of heavy equipment and construction personnel in the area. PLEASE NOTE: Conditions are subject to change without notice. Double fines for speeding in work zones may be in effect.

White Sands Missile Range Notification

For information regarding closures, you may call WSMR at 678-1178 or 678-2222 for updates.

Interstates: 

I-25 Guardrail Replacement Project, Mile Marker 6 to 14.2, Las Cruces to Dona AnaLC00384

J-H Supply Company, Inc. (Contractor) will be continuing a guardrail and concrete barrier wall project on Interstate 25 from Las Cruces to just north of Doña Ana. Traffic Control and lane closures will be in place 24/7 in both directions for guardrail removal and replacement. Crews are currently installing concrete barrier walls. Speed limits will be reduced throughout the project. Contractors' working hours are Monday through Friday from 6 a.m. to 5 p.m. 

I-25 Roadway Rehabilitation Project, Mile Marker 75 to 85, T or C CN 1102320/1102330

Mountain States Constructors Inc. (Contractor) will be finalizing a roadway reconstruction project on I-25 from mile marker 75 (Williamsburg) to mile marker 85 (Cuchillo). Lane closures will be in place as needed for striping, and rumble strips to be installed. Traffic should expect reduced speed limits. Contractor's working hours will be 6 a.m. to 6 p.m. Monday through Friday. 

I-25, Lane Closures, Mile Marker 40 to 42, Hatch

Emergency Environmental Services, (Contractor) will have lane closures in place along I-25 from mile marker 40 to 42 on the northbound and southbound passing lanes for median repairs. Speed limits will be reduced to 55 mph in the work zone.  Lane closures will be in place from 7 a.m. until 5 p.m. Monday through Friday. 

I-10, Pavement Preservation, Mile Marker 85 to 116, Deming

Dismuke Construction Co., (Contractor) will be continuing a crack sealing operation on I-10 from exit 85 working east towards exit 116. Lane closures will be in place in both the eastbound and westbound lanes as needed. Please expect reduced speed limits in the construction zones. Crews will be working seven days a week from 7 a.m. to 6 p.m. 

US Roadways:

State Roadways:

NM 189, Utilities, Mile Marker 1 to 6, Hatch to Salem

ITG Communications (Contractor) will be placing utilities along NM 189 from Vado to NM 28, and crossing the intersection at NM 478. A flagging operation will be in place with expected wait times of 15 minutes. Utility work will be Monday through Friday from 8am to 4 p.m. Work is expected to be completed by December 28, 2026.

NM 460, Roadway Rehabilitation, Mile Marker 0 to 1.6, Anthony

Intermountain Slurry Seal (Contractor) has completed operations. Pavement markings are scheduled to be installed as soon as possible. 

NM 273, Roadway Rehabilitation, Mile Marker .8 to 6, Sunland Park

Mountain States Constructors Inc. (Contractor) has resumed the roadway rehabilitation project on NM 273 (McNutt Rd.) in both the northbound and southbound lanes from mile marker 0, Texas State Line to mile marker 6, 1 mile south of Santa Teresa. Speed limits will be reduced throughout the project. Contractor's working hours will be 6 a.m. to 6 p.m. Monday through Friday. 

NM 26, Pavement Preservation and Centerline Rumble Strips, Deming to Hatch1102360

Hasse Contracting Company Inc. (Contractor), motorists should expect daytime lane closures and a pilot car operation in both directions on NM 26 from mile marker 10 towards mile marker 46 in Hatch as crews complete crack sealing, fog sealing, and installation of centerline rumble strips. A temporary Traffic signal will be set up during daytime operations; please follow instructions. As part of NMDOT's Target Zero initiative, centerline rumble strips are being installed to help reduce head-on and crossover crashes by alerting inattentive drivers who drift across the centerline. Work is scheduled from 6:30 a.m. to 7 p.m., Monday through Friday, with the possibility of weekend work as needed.

NM 213 & NM 404, Roadway Widening, Mile Marker 0 to 2, Chaparral E100321/322

FNF Construction Inc. (Contractor) is continuing with the reconstruction and improvement project on NM 404 and NM 213 from the roundabout to near the Texas state line. Crews will continue to implement temporary flagging and mobile traffic control as needed. NM 404 traffic is pushed to the inside lanes on the eastbound and westbound lanes for about a mile west of the roundabout. This will be in place for about three months as crews work on Phase I of construction. Traffic on NM 213 is shifted to the east, with crews working in the southbound lane and shoulders to install a temporary barrier wall. One lane of traffic is open in each direction as crews continue installation of fencing, guardrails, boxes, and cattle guards, as well as preparing for bridge replacement and MSE (mechanically stabilized earth) walls. The speed limit is reduced to 45 mph throughout the construction zone. Motorists should expect delays and allow extra time to reach their destinations. Regular work hours are Monday-Friday 6 a.m.-6 p.m., although the contractor may work longer hours or on weekends as needed. For more information, visit: https://www.dot.nm.gov/nm-213-nm-44-intechange-project/ 

Chip Seal Projects, Luna Co:

The New Mexico Department of Transportation (NMDOT) will be completing Chip Seal operations on roadways in the Deming area of Luna County. During operations, drivers can expect flagging personnel, pilot vehicles, and temporary stops. Brooming will occur during and after the sealing process. Loose gravel may remain on road surfaces for a few days post-treatment. Work will take place Monday through Friday, from 7 a.m. to 5 p.m. Note that center striping will be absent in work zones until completion. Crews are currently waiting for final striping on the roadway listed below.

Various I-10 Frontage Roads (Akela area)

City of Las Cruces Projects:

Spruce/Telshor/Triviz Intersection Improvements

Lane closures will be in place for northbound commuters on Triviz Drive between Spruce Avenue and Redwood Street, and for westbound commuters on Spruce Avenue between Telshor Boulevard and Wingate Road. The lane closures will be in place until approximately December 18, 2026.

TXDOT I-10 Project:

I-10 Widening West, Phase 2

Saturday, November 21 to Monday, November 23 (51hr Closure)

3 AM (Sat) to 6 AM (Mon)

    Full closure of I-10 Eastbound from Anthony to Transmountain

Crews will be placing bridge deck

Saturday, December 5 to Monday, December 7 (51hr Closure)

3 AM (Sat) to 6 AM (Mon)

    Full closure of I-10 Eastbound from Anthony to Transmountain

Crews will be placing bridge deck

Artcraft Project

Monday, November 23, through Wednesday, November 25, 9 AM to 4 PM (as needed)

    Alternating left and right lane closures Artcraft EB and WB from NM State line to Doniphan.

Crews will be working on ITS/Illumination and MSE Wall Installation.

9 AM to 4 PM (as needed)

    Alternating left and right lane closures N. Desert from Helen of Troy Dr. to Cheddars Restaurant.     Alternating left and right lane closures S. Desert from Charlie Clark Nissan to Blue Sky Dr.

Crews will be Forming Bent Caps

 9 AM to 4 PM (as needed)

    Alternating Left and Right Lane closures on 1-10 WB and EB from Redd Road to Transmountain

Crews will be working on Median Columns Steel and Erecting Formwork

Borderland Expressway Phase 2

Closures 11/23/26 through 11/27/26

Monday, November 23 through Tuesday, November 24, Daily, from 6 a.m. to 6 p.m.

Alternate Lane closures on US54 EB/WB between Mesquite Hills and McCombs. Mesquite Hills reduced to one lane between US54 and Red Man Dr. Flaggers will be on site directing traffic as needed for haul trucks crossing Mesquite Hills.

Daily, from 7 a.m. to 5 p.m.

Flaggers will be on site directing traffic as needed for haul trucks crossing at McCombs and Stan Roberts.

Crews will be performing bridge work and transporting earth embankment into the project.

TXDOT Roadway Closures can be found at www.drivetexas.com 

ADOT I-10 Project:

The Arizona Department of Transportation advises drivers to prepare for the start of a pavement improvement project on east- and westbound Interstate 10, between San Simon and the New Mexico state line in Cochise County.

Crews will begin mobilizing for construction starting Monday, Nov. 23, with daily work hours from 6 a.m. to 4 p.m. Monday through Thursday and 6 a.m. to noon Friday. 

Intermittent lane restrictions on east- and westbound I-10 between mileposts 377 and 391 are scheduled to begin early December.

Motorists traveling through the area can expect traffic restrictions and reduced speed limits for the duration of the project. ADOT will provide advance notice of lane restrictions and closures to email subscribers.

Drivers should allow extra travel time, use caution, be prepared to slow down and merge safely when approaching and traveling through all work zones.

For more information and to subscribe for project updates, visit the project website at https://azdot.gov/i10SanSimonNewMexico. 

ADOT's Traveler Information Site at www.az511.gov , download the AZ511 app or call 511.