In all construction zones, motorists are asked to reduce speed, obey posted signs, and use extreme caution, as well as continuing to be cautious of heavy equipment and construction personnel in the area. PLEASE NOTE: Conditions are subject to change without notice. Double fines for speeding in work zones may be in effect.

White Sands Missile Range Notification

For information regarding closures, you may call WSMR at 678-1178 or 678-2222 for updates.

Interstates: 

I-10 Bridge Repairs, Mile Marker 24, Lordsburg

Hasse Construction Co. (Construction) will begin reconstruction of the I-10 bridge at exit 24, winter 2025. Eastbound traffic must utilize exits 20 (Lordsburg West) or 22 (Lordsburg Main Street) for access to business. 

I-10 Roadway Rehabilitation Project, Mile Marker 35 to 44, Separ CN1101900

Mountain States Constructors, Inc. (Contractor) will be finalizing a roadway rehabilitation project on Interstate 10 from milepost 35 (10 miles east of Lordsburg) to milepost 44 (Separ) in Grant County. Drivers can expect various daytime lane closures on both the eastbound and westbound lanes as needed for concrete barrier wall and guardrail operations. A 12' width restriction is in place throughout the project, overside loads will need to be permitted. The contractor's hours of operation will be from 6 a.m. to 6 p.m., Monday through Friday. 

I-10 Bridge & Roadway Rehabilitation Project, Mile Marker 140 to 143, Las Cruces CNLC00371

La Calerita Construction, LLC. (Contractor) will be finalizing a bridge rehabilitation project on I-10 over the University Ave Interchange, milepost 141.  High-mast lighting is scheduled to be installed on November 10, 2025. Lane closures will be in place on the northbound right driving lane of Main St., and the eastbound right driving lane of University Ave. These lane closures will be in place until Tuesday, November 11, 2025, at 6 p.m. 

I-25 Business Loop Roadway Rehabilitation Project, Williamsburg to T or C

This upcoming safety initiative will modify the roadway striping to mitigate municipal safety concerns about fire truck access while still addressing the key concerns identified in the safety plan.  The road diet enhancement project does specifically target traffic calming and driver guiding to enhance safety for all roadway users. 

New Pavement Markings: We're reconfiguring the road markings to mitigate municipal safety concerns while maintaining the road diet concept. Upgraded Signs & New Installations: Keep an eye out for new and clearer signs to guide you along the road with ease. Delineator Systems: These new markers will improve visibility and prevent vehicles from accidentally entering into the bikeway. Other Construction Enhancements: Various updates, including radar speed feedback units, will support the road users, ensuring smoother and safer traffic flow for everyone.

What's Next: These upgrades will be observed and evaluated to determine if future improvements would further enhance the safety on the road. This project has been funded through the NMDOT Highway Safety Improvement Program (HSIP) and will be let for construction in the Winter of 2025.

US Roadways:

US 70 Roadway Rehabilitation, Mile Marker 149 to 150 Las Cruces LC00271

El Terrero Construction, LLC. (Contractor) is finalizing the project to make roadway improvements to US 70 North Main Street between Spitz/N. Solano Drive and the intersection of N. Triviz Drive/Elks Drive. Lane closures will be required as needed for project finalization. Working hours will be overnight from 7 p.m.-6:30 a.m. This project is expected to be completed by the end of November 2025, visit www.us70mainstreet.com

US 180 Roadway Reconstruction Project, Mile Marker 123 to 128, Hurley, CN#1101841

Mountain States Constructors, Inc., (Contractor) will be finalizing with the roadway reconstruction project along US 180 from milepost 123.13 in Bayard to milepost 128.27 in Hurley.  Various lane closures and alternating traffic patterns may be in place for cleanup operations. Speed limits are reduced throughout the project to 45 mph; this project is a double fine zone. The contractor's working hours are Monday through Friday from 7 a.m. to 5 p.m. and crews may work on Saturdays. 

US 180 Signalization, Lighting Project, Mile Marker 113.140 to 118.951, Silver City CN#1101841

RT Electric, Inc. (Contractor) will be continuing with the installation of roadway lighting and signalization along US 180 in Arenas Valley. Shoulder work will be in place for the contractor to trench for conduit installation and concrete bases. Areas of narrow shoulders may require lane closures. Contractors' working hours are Monday through Friday from 6:30 a.m. to 5 p.m. and they may work on Saturdays, depending on the weather conditions. This project is expected to be completed by winter 2025. 

US 180 Signalization Project, US 180 and Gold at Railroad, Pine, Cedar & Ash St., Deming

RT Electric, Inc. (Contractor) will be continuing with the installation of roadway signalization, curb & gutter, new ADA ramps, median curbs, signage and striping along US 180 and Gold Street at Railroad, Pine, Cedar and Ash St. Shoulder work and lane closures will be in place for the safety of the contractor and traveling public. Lane closures in the driving lanes along Pine Street at the Gold St. intersection will be in place for the safety of the traveling public and work crews. Sidewalk closures should be expected. Contractors' working hours are Monday through Friday from 6:30 a.m. to 5 p.m. This project is expected to be completed by December 2025. 

State Roadways:

NM 101, University Ave Multimodal Project, Mesilla LC00290

La Calerita Construction, LLC. (Contractor) will be continuing the multi-modal project on University Avenue/New Mexico State Road 101 from Avenida de Mesilla to South Main Street. Phase 3 Construction has begun. Traffic Impacts: During this phase, the following traffic impacts will be in place:

Only one lane of eastbound traffic will be open on NM 101 (University Ave) between Avenida de Mesilla and S Main Street Traffic heading westbound will be detoured to W Union Ave.

Boldt Street is open first to provide access to eastbound University Ave/NM 101 with Teresita Street closed. 

Then, Teresita Street will be open, and Boldt Street will be closed. Both streets will not be closed at the same time. Also, currently Old Farm is closed, and Stanford is open. When construction is completed near Old Farm, it will be opened, and Stanford will be closed. Streets will not be closed at the same time to provide access to eastbound University Ave/NM 101.

Regular work hours are Monday-Friday 7 a.m.-4:30 p.m. although the contractor may work longer hours or on weekends as needed. Additional construction will follow this phase, with the project expected to be completed in fall 2026. All construction is weather permitting and is subject to change without notice.

For more information visit https://www.dot.nm.gov/universitynm101/  

NM 136, Power Line Placement, Mile marker 7.33, Santa Teresa

El Paso Electric Co. (Contractor) will be setting new poles in the right of way and running a power line over NM 136 at Mile Marker 7.33. Traffic control will be handled by Apache Barricade with the assistance of NM State Police. Closure is expected to take place by November 27, 2025, from the hours of 8 a.m. to 4 p.m. 

NM 549, Roadway Rehabilitation, Deming

Mountain States Constructors, Inc. (Contractor) will be continuing roadway rehabilitation project on NM 549 from milepost 24 to 31.  Drivers can expect lane closures on both the eastbound and westbound lanes of NM 549 as needed. A traffic signal with a pilot car operation will be in place, please reduce your speed and obey traffic control devices. Roadway will be restricted to 12-foot for oversized loads. The contractor's hours of operation will be from 6:30 a.m. to 7 p.m., Monday through Saturday, with the possibility of some weekend work. 

NM 273, Utility Work, Mile Marker 6 to 9, Santa Teresa

Nine Degree Construction (Contractor) will have lane closures in place on NM 273 and NM 136 for Utility placement. Speed limits will be reduced, please obey traffic control devices. The contractor's hours of operation will be from 7 a.m. to 4:30 p.m. Monday through Friday. Drivers should expect delays and plan accordingly. This project is expected to be completed by December 8, 2025. 

NM 169, Sewer Line Installation, Mile Marker 23 to 29, Alamo

SmithCo Construction (Contractor) will be installing a sewer line along NM 169 from mile marker 23 to 29, shoulder work with occasional lane closures may be in place. Working hours are from 7 a.m. to 5:30 p.m. and work is expected to be completed by March 30, 2026.

NM 11, Box Culvert, Mile Marker .08, Columbus Port of Entry

Morrow Ent. Inc. (Contractor) will be constructing a concrete box at the intersection of NM 11 and El Paso Ave, just north of the Port of Entry. Speed limits will be reduced, please obey traffic control devices. The contractor's hours of operation will be from 6:30 a.m. to 6 p.m. Monday through Friday and work is expected to be completed by November 26, 2025.

Chip Seal Projects, Luna Co:

NM 9, Fog Sealing, Mile Marker 51 to 116, Columbus

NMDOT Maintainers will be assisting Seal Master with Fog Sealing operations on NM 9 from Animas to the Dona Ana/Luna County line. A pilot car operation will be in place. Hours of operation will be Monday to Thursday from 7 a.m. to 5 p.m. Reduced speeds and no center striping will be in place until completion of all projects. 

Fog sealing on NM 81 is complete; striping will be completed by mid to late November. Speed limits will remain reduced until striping has been completed. 

City of Las Cruces Projects:

Casa Linda Acres Subdivision

As part of the Casa Linda Acres Reconstruction Project, Spartan Construction of NM, LLC, will be maintaining road closures on Avenida Blanco from South Valley Drive to Calle Del Encanto, and on Calle Del Sol from Avenida de Mesilla to West Brown Road. Closures will be implemented through January 2, 2026. Access will be maintained for residents; motorists are urged to follow all posted signs.

N. Melendres St.

Las Cruces Motorist are advised that N. Melendres St. between W. Hadley Ave. and W. Mountain Ave. is scheduled to undergo roadway and utility improvements by A-Mountain Construction as part of the City of Las Cruces N. Melendres St. Reconstruction Project. Work will begin September 15, and the closure is estimated to last approximately 3 months in duration for phase 1. During construction, access to N. Melendres St. will not be permitted to through traffic. Signage and detours will be present directing traffic around the work zone.

East Mesa Roads & Drainage - Cortez Drive Improvements 

As part of the Cortez Drive Improvements, roadway, storm drainage, and utility improvements will be conducted by Caliper Construction (Contractor) on Cortez Drive between Porter Drive and Dunn Drive. Cortez will be closed to through traffic. Detours will be in place directing traffic around the road closure. Access will be maintained for residents; motorists are urged to follow all posted signs. The entire project is estimated to be completed by December 2025. 

TXDOT I-10 Project:

I-10 Widening West

Closure Information for THIS weekend:

Saturday, November 8 through Monday, November 10

5 a.m. to 5 a.m. (48-Hour Weekend Closure)

I-10 westbound at Mesa closed I-10 eastbound at Redd closed

Detour: Westbound traffic will exit at Mesa and continue to North Desert through Mesa, Thorn, and Redd intersection and re-enter I-10 westbound after Redd.

Crews will be removing PTCB, remove/replace asphalt inlet patches with concrete on I-10 eastbound, final striping, install OSB structure (full width across I-10), and open I-10 westbound off-ramp.

Closure Information for NEXT weekend:

Saturday, 11/15/25 to Monday, 11/16/25

5 a.m. to 5 a.m. 48 HOUR WEEKEND CLOSURE 

Close I-10 WB at Mesa Close 1-10 EB at Redd

Detour: WB Traffic will exit WB Mesa (Ramp 10) and continue to North Desert through the Redd Rd. intersection and re-enter WB I-10 after Redd Rd.  EB Traffic will exit at Redd and use South Desert to re-enter EB I-10 at Mesa (EB Ramp 10 EB).

Crews will be removing PTCB, final striping, and painting barrier. 

TXDOT Roadway Closures can be found at www.drivetexas.com.